
Completed works (looking north).
A road development scheme in a sensitive location in Co. Donegal
ROD was engaged by Donegal County Council to provide construction and handover stage consulting engineering services for this road development scheme located just north of Glenties, at the north-west edge of the Blue Stack Mountains. The appointment was made under the Transport Infrastructure Ireland (TII) Technical Consultancy Services Framework Lot 1C.
The scheme comprises:
Construction began in early 2021, with Wills Bros Ltd. as the main contractor, and was largely completed by November 2022.
The project was shortlisted for International Project of the Year at the Ground Engineering Awards 2023.
Innovative geotechnical construction solutions, including the staged construction of large embankments on very soft peat soils, were implemented on the project to mitigate the risk to sensitive environmental receptors.
In demonstrating how peat excavations can be avoided, this project signals the potential for developing sustainable geotechnical engineering solutions that reduce greenhouse gas emissions from excavated peat (depending on import material costs and transport needs).
The open and collaborative approach adopted by the office, site and construction staff resulted in the successful mitigation of environmental restrictions, construction of 6m+ high embankments on extremely low strength peat and the safe delivery of the scheme.
In addition to fulfilling our responsibilities as Employer’s Representative, our team oversaw:
The project team undertook supplemental investigations, conducted risk analysis based on geophysical profiling, and carried out piezometric cone penetration testing and specialist laboratory scheduling on undisturbed samples obtained from locations of specified instrumentation.
Discussions with the original designer, client and contractor produced several improvements, including changes in geosynthetic materials specifications and detailing.
Supplemental site and laboratory testing informed stability analyses and allowed us to improve the detailing and filling rate criteria used to mitigate the reduced peat strength observed on-site.
While significant embankment settlements of up to 1.5m high were observed during construction, overall stability was controlled by the observation of lateral movements and pore water pressures.
A temporary works crossover was constructed to minimise risk to users of the temporary road while excavation of the cutting section, through the adjacent peat and in areas outside the catchment, was ongoing.
The scheme involved construction close to and within the West of Adara/Maas Road Special Area of Conservation (SAC) and the Owenea catchment, where freshwater pearl mussels have been recorded. To ensure compliance with planning conditions, our ecological Clerk of Works (eCOW) visited the site and carried out audits of the contractor’s environmental mitigation measures.
The risk of potential impacts to the highly sensitive aquaculture was a key consideration and necessitated the avoidance of peat excavations.
Detailed ground investigation information was limited at several key locations on site.